In the past few months, comprehensive works have been done on all planned activities within the Contract "The construction of an SVC facility at substation Konjsko” signed between HOPS and Siemens Energy d.o.o. All major equipment was delivered to the site. The installation of the SVC transformer, SVC facility (outer part), and equipment foundations are completed until now. Reinforced concrete works of the SVC facility, as well as installation of primary and secondary equipment, are also finished.
In the forthcoming months, the installation of remaining components, testing, and commissioning on the SVC facility will be carried out.