In substation Divača, the contractors completed the installation of the energy capacitor, which took place intensively in July. Now follows the works in the 400 kV field. The connection of the device to the network is scheduled for December 2020.
Energy capacitor with fixed power of 100 Mvar, together with other compensation devices, will enable voltage regulation in the electricity system of Slovenia and Croatia.