All high-voltage 400 kV equipment was installed on the 400 kV field for the Mechanically Switched Capacitor with Damping Network (MSCDN) in the Divača substation. After completing high-voltage equipment installation, we will start with cabling, testing, and secondary equipment parameterization. We plan to complete the work by the end of March when the energy capacitor is ready for operation.